For a Proper experience on Trainspy.com, enable JavaScript in your browser

Search For Trains   

PENDEKALLU

STATION INFO

Address: Pendekallu Junction Station, Andhra Pradesh 518468, India

Station Code: PDL)PENDEKALL

Station Name: PDL)PENDEKALLU

Zone: SCR/South Central

Total Unique Trains: 14

Train Frequency Weekly: 85

Station Traffic: Medium

ALL PASSING TRAINS
Print Table

To Check Ticket Availibility Click Classes
TrainTrain NameArrDepHaltDaysClasses
Arrival
17225AMARAVATHI EXP04:2404:251M,TU,W,TH,F,SA,SU2A,3A,SL,GN
77414GTL KRNT PASS05:2305:241M,TU,W,TH,F,SA,SUUNRESERVED
57426GTL KCG PASS06:3406:351M,TU,W,TH,F,SA,SUUNRESERVED
56504BZA BNC PASS06:4406:451M,TU,W,TH,F,SA,SUSL,GN
56502UBL BZA PASSR07:1907:201M,TU,W,TH,F,SA,SUSL,GN
77415KRNT GTL PASS09:4409:451M,TU,W,TH,F,SA,SUUNRESERVED
77409GTL DHNE PASS12:2612:271M,TU,W,TH,F,SA,SUUNRESERVED
77410DHNE GY PASS14:2714:281M,TU,W,TH,F,SA,SUUNRESERVED
77411GY DHNE PASS15:5916:012M,TU,W,TH,F,SA,SUUNRESERVED
56503VIJAYAWADA PASS17:3917:401M,TU,W,TH,F,SA,SUSL,GN
57425KCG GTL PASS17:3917:401M,TU,W,TH,F,SA,SUUNRESERVED
56501HUBLI PASS18:4218:442M,TU,W,TH,F,SA,SUSL,GN
17226AMARAVATI EXP19:1919:201M,TU,W,TH,F,SA,SU2A,3A,SL,GN
77413KRNT GTL PASS20:3920:401M,TU,W,TH,F,SA,SUUNRESERVED
TrainTrain NameArrDepHaltDaysClasses
Departure



RECENT NEWS

1
   

SOUTH CENTRAL RAILWAY
PRESS RELEASE
PUBLIC RELATIONS OFFICE, SECUNDERABAD - 500 071
No.07/2020-2115-04-2021
Secunderabad
Commissioning of Doubling with Electrification between Donakonda - Gajjelakonda





- Part of Guntur - Guntakal Doubling & Electrification Project

The Double line works along with electrification between Donakonda – Gajjelakonda for a distance of 12.4 Kms has been completed & commissioned yesterday i.e., 1st April, 2021, as a part of the Guntur - Guntakal Doubling & Electrification Project. The speed trial inspection has been successfully carried out by Commissioner of Railway Safety and the section is initially permitted with maximum permissible speed of 90 Kmph.

The Guntur - Guntakal Section is vital rail link connecting the coastal belt of Andhra Pradesh State with Rayalaseema region and beyond south. In order to provide seamless transportation and ease the congestion o­n this section, Guntur - Guntakal Doubling & Electrification project was sanctioned. As part of it, doubling & electrification between Nallapadu – Satulur (32 kms) and Dhone – Pendekallu- Edduladoddi (36.6 Kms) has already been completed and commissioned.

Now, with the completion of another 12.4 Kms between Donakonda – Gajjelakonda, a total of 81 Kms length of doubling works with electrification has been completed o­n the Guntur – Guntakal section. Works in the remaining sections are in fast progress. As part of the Donakonda – Gajjelakonda doubling works, Centralised Electronic Interlocking system has been provided at Donakonda and Gajjelakonda stations for efficient handling of the trains.

The Benefits of the Project are –

1. Potential for running more number of trains between Guntur-Guntakal, particularly from Hyderabad/Nadikude side towards Rayalaseema region and beyond down South.

2. The enhanced connectivity will help in improving the Socio-economic condition of the region, particularly for people of Guntur, Prakasam, Kurnool and Anantapur districts.

3. Improves freight transportation by harnessing the potential of mineral rich Palnadu Region to transport its produce/goods to any part of the country.

4. Doubling of this section enhances overall train handling capacity in the Guntur/Vijayawada region, with the possibility of diverting more trains via Guntur to balance the rail traffic and reduce the congestion o­n the Grand Trunk route.

Shri Gajanan Mallya, General Manager, SCR congratulated all the Officials and staff involved in the completion of the project. He stated that the doubling and electrification project of Guntur - Guntakal section is o­ne of the major projects being carried out by the Zone and the completion of entire stretch will ease congestion and paves the way for smooth operation of train services.



(Ch. Rakesh)
Chief Public Relations Officer




2
Press Release No. 38519-02-2021
Hubballi
Press Release No. 385, EXTENSION OF THE SERVICES OF TRAINS

                                       दक्षिण पश्चिम रेलवे/ SOUTH WESTERN RAILWAY

        प्रेस विज्ञप्ति/ Press Release No. 385  Dt: 18.02.2021                     

EXTENSION OF THE SERVICES OF TRAINS

The services of following trains will be extended as detailed below:-

1.  Service of Train No. 02785Kacheguda – Mysuru Superfast Express special from Kacheguda will be extended further from 01.04.2021 to until further advice. There will be no change in timings, Path and composition of the train.


2.  Service of Train No. 02786 Mysuru – Kacheguda Superfast Express special from Mysuru will be extended further from 02.04.2021 to until further advice. There will be no change in timings, Path and composition of the train.


3.  Service of Train No. 07225 Vijayawada – SSS Hubballi Special Express from Vijaywada will be extended further from 01.04.2021 to until further advice. There will be no change in timings, Path and composition of the train.


4.  Service of Train No. 07226 SSS Hubballi - Vijayawada Special Express from SSS Hubballi will be extended further from 02.04.2021 to until further advice. The timings of this train will be revised as under:-

Train No. 07226 Hubballi - Vijayawada Special Express will depart from SSS Hubballi at 13:30 hrs and arrive Vijayawada at 05:40 hrs o­n the next day.

Enroute The train will arrive/depart Annigeri - 13:56/13:57 hrs, Gadag- 14:24/14:26 hrs, Koppal - 15:18/15:20 hrs, Munirabad - 15:39/15:40 hrs, Hosapete - 15:55/16:00 hrs, Torangallu - 16:34/16:36 hrs, Ballari - 17:28/17:30 hrs, Guntkal - 18:47/18:50 hrs, Pendekallu - 19:29/19:30 hrs, Dhone- 19:48/19:50 hrs, Nandyal- 21:30/21:35 hrs, Giddalur- 22:33/22:34 hrs, Cumbum- 23:10/23:11 hrs, Markapur Road - 23:32/23:33 hrs, Donakonda- 23:55/23:56 hrs, Vinukonda- 00:30/00:31 hrs, Narsaraopet- 00:58/00:59 hrs and Guntur- 03:10/03:20 hrs.

All the norms of the State and Central Government regarding Covid-19 including social distancing, sanitization etc., should must be followed in the trains and at the Railway stations. The train will have fully reserved service and the fare structure is 1.3 times of fare.


                                                                   Chief Public Relations Officer                                                                    South Western Railway, Hubballi