For a Proper experience on Trainspy.com, enable JavaScript in your browser

Search For Trains   

Chikkamagaluru

STATION INFO

Address: Railway Approach Road, Chikkamagalur Karnataka

Station Code: CMGR)Chikkamagalur

Station Name: CMGR)Chikkamagaluru

Zone: SWR/South Western

Total Unique Trains: 4

Train Frequency Weekly: 25

Station Traffic: Low

ALL PASSING TRAINS
Print Table

To Check Ticket Availibility Click Classes
TrainTrain NameArrDepHaltDaysClasses
Arrival
56278YPR CMGR PASS21:15Des--M,TU,W,TH,F,SA,SUUNRESERVED
56271SMET CMGR PASS22:10Des--M,TU,W,TH,F,SA,SUUNRESERVED
TrainTrain NameArrDepHaltDaysClasses
Departure
56277CMGR YPR PASSSrc07:40--M,TU,W,TH,F,SA,SUUNRESERVED
56272CMGR SMET PASSSrc06:40--M,TU,W,TH,F,SA,SUUNRESERVED



RECENT NEWS

1
Press Release No. 14219-06-2020
Hubballi
Press Release No. 142, MAJOR CANAL CROSSING BRIDGE OF UPPER BHADRA DAM BETWEEN SHIVANI AND AJJAMPURA STATIONS COMPLETED IN RECORD TIME BY SWR

प्रेस विज्ञप्तिPress Release No. 142  Dt: 17.06.2020

MAJOR CANAL CROSSING BRIDGE OF UPPER BHADRA DAM BETWEEN  SHIVANI AND AJJAMPURA STATIONS COMPLETED IN RECORD TIME BY SWR

Safety in train operations is of utmost importance and all track maintenance work o­n SWR is being carried out diligently braving all odds.   Safety and maintenance work of all assets are also being taken-up o­n its network.

Taking advantage of the unprecedented lockdown due to Covid-19 and consequent suspension of passenger trains, a major canal crossing bridge of upper Bhadra Dam between Shivani and Ajjampura in Bengaluru – Hubballi line has been completed o­n 17.06.2020. The work of canal crossing was planned and carried out by Mysuru division under the able leadership of Smt. Aparna Garg, DRM/Mysuru.

The major work canal crossing for construction of precast RCC twin box and insertion by Box Pushing Method was sanctioned at a cost of Rs.14.72 Cr. as a deposit work by the State  Government  of Karnataka. This was necessary to supply water to the districts of Chikkamagaluru, Chitradurga, Tumakuru and Davanagere. The work was started last year but due to falling of black cotton soil in unprecedented trains endangering the embankment, work was forced to be stopped.

Shri Suresh Angadi, Hon’ble MOSR has taken keen initiative o­n request of Shri Narayana Swamy, Hon’ble MP, Chitradurga, and elected representatives of the region and advised SWR to complete the work in the shortest possible time before the monsoons to help in irrigation of land which was livelihood of farmers of this region.

The work was first proposed to be taken up by suspending train services o­n this line. As advised by Hon’ble MoSR, GM/SWR has inspected the site in the 2nd week of May and instructed that the work should be carried out by laying temporary diversion of running track to keep the movement of rail traffic considering the movement of freight / parcel / goods services.

The diverted track was laid in just 16 days time and the Box pushing for 24 meters length was completed in 7 days. A temporary arrangement for diversion of traffic through diverted track was done through temporary single line working in this double line section. Both lines were re-commissioned in 3 days.  Engineering Branch officers of Mysuru division, Shri Ravichandran, Sr.DEN/Co-rd and Shri Venkat Rao, Sr.DEN/N have been instrumental in completing the work in time.

Shri A. K. Singh GM/SWR informed that in the challenging circumstances too, Railway staff have worked o­n war footing basis and could complete the canal crossing below railway track for flow of water from upper Bhadra dam.

The canal crossing below railway track will facilitate water from Bhadra dam to the four districts of Chikkamagaluru, Chitradurga, Tumakuru and Davanagere.  This canal irrigates 2,25,000 hectares of land o­n downstream side and it serves in filling of 367 tanks in the downstream side covering four districts. The entire work of has been completed in a record 26 days duly utilizing the COVID 19 lockdown period.   The work would have otherwise taken not less than 90 days and could have got further delayed by monsoon.  In addition passenger trains also would have to be cancelled/detained o­n this account.


                                                                                          Chief Public Relations Officer

                                                                              South Western Railway, Hubballi





2
Press Release No. 65 Dt:2.05.202003-05-2020
Press Release No. 65 Dt:2.05.2020, CONSTRUCTION OF LIMITED HEIGHT SUBWAY AT LEVEL CROSSING NO.135 ON BIRUR- CHIKJAJUR SECTION OF MYSURU DIVISION OF SWR DURING COVID-19 LOCKDOWN


प्रेस विज्ञप्ति/ Press Release No. 65 Dt:2.05.2020


CONSTRUCTION OF LIMITED HEIGHT SUBWAY AT LEVEL CROSSING NO.135 o­n BIRUR- CHIKJAJURSECTION OF MYSURU DIVISION OF SWR DURING COVID-19 LOCKDOWN


 

SWR is working round the clock during lockdown to ensure that all safety and maintenance work are taken-up o­n its rail network. The Covid-19 Pandemic has frozen the country during the lockdown, but the national carrier continues to work carrying out all priority and urgent works. Railway workforce continues to work round the clock by running freight and parcel trains to reach essential goods, commodities and medical items across the country.

 Safety at level crossing is o­ne of the priority items of Shri Suresh Angadi, Hon’ble MoSR.As directed by Hon’ble MoSR all safety and maintenance works are being taken up during the extended Lockdown. This is a step towards Railways mission of eliminating LC gates and ensuring safety at level crossings. The extended lockdown has provided the opportunity to carry out works without causing inconvenience to the public during the otherwise busy train operations.

The work of construction of Limited Height Subway (LHS) at LC no. 135 between Nagavangala & Ajjampura stations was completed o­n 30.04.2020 and opened to road traffic.This Subway connects two villages Giriyapura and Channapura of Chikkamagaluru District. Construction of limited height subway had been a long pending demand of the people of these two villages.Due to the busy railway crossing gate, road traffic was often closed and general public were faced with difficulty of waiting at this LC tillmovement of train services were completed . The Limited Height Subway (LHS) has been constructed at a cost of Rs.1.9 cr.The construction of Limited Height Subway (LHS) at LC no. 135 will improve mobility and safety in addition to convenience of local public in general.

This Limited Height Subway (LHS) was constructed by insertion of 12 precast RCC boxes duly utilizing traffic block and, construction of wing walls were completed just before declaration of the Lockdown.During the lockdown period, work could be carried o­n without any restriction of traffic blocks and in this period 240 m long approaches were completed. Mysuru Division of SWR executed road work during the lockdown taking permission from the State governmentto collect 4800 bags of cement, 320 MT of steel and daily water required for concrete curing duly maintaining social distancing and all hygienic standards


                                                                                    Chief Public Relations Officer

                                                                              South Western Railway, Hubballi