For a Proper experience on Trainspy.com, enable JavaScript in your browser

Train Search








12 Trains from (KNE)KISHANGANJ to (SVQ)Sivok


Address: Kishanganj, Bihar, India

Station Code: KNE

Station Name: KISHANGANJ

Zone: NFR/Northeast Frontier

Train Frequency Weekly: 357

Station Traffic: High

Address: National Highway 31, Sevoke Bazar, Sevoke , Dist - Darjeeling West Bengal

Station Code: SVQ

Station Name: Sivok

Zone: NFR/Northeast Frontier

Train Frequency Weekly: 59

Station Traffic: Medium





Trains
To Check Ticket Availibility Click Classes
TrainTrain NameFromDepToArrTimeDaysClassesStatus
13149KANCHANKANYA EXPKNE05:42SGUJ08:052:23M,TU,W,TH,F,SA,SU2A,3A,SL,GN,13149 Status
15719INTERCITYKNE08:14SGUJ11:153:01M,TU,W,TH,F,SA,SU2S,GN,15719 Status
13248KYQ CAPITAL EXPKNE09:52SGUJ12:452:53M,TU,W,SU1A,2A,3A,SL,GN,13248 Status
75707RDP NJP DEMUKNE10:02SGUJ12:452:43M,TU,W,TH,F,SA,SUUNRESERVED75707 Status
15661RNC KYQ EXPRESSKNE10:52SGUJ13:352:43W2A,3A,SL,GN,15661 Status
15941JHAJHA DBRG EXPKNE10:52SGUJ13:352:43F2A,3A,SL,GN,15941 Status
15484MAHANANDA EXPKNE12:10SGUJ15:103:00M,TU,W,TH,F,SA,SU2A,3A,SL,GN,15484 Status
75719MLFC SGUJ DMUKNE13:02SGUJ16:002:58M,TU,W,TH,F,SA,SUUNRESERVED75719 Status
15463BLGT NJP INTERCITYKNE16:52SGUJ19:152:23M,TU,W,TH,F,SA,SUUNRESERVED15463 Status
15643PURI KYQ EXPRESSKNE17:37SGUJ19:452:08SA2A,3A,SL,GN,15643 Status
75743KIR SGUJ PASSKNE21:05SGUJ00:103:05M,TU,W,TH,F,SA,SUUNRESERVED75743 Status
22501NEW TINSUKIA EXPKNE22:05SGUJ00:102:05TU2A,3A,SL,GN,22501 Status
Train Type Train Table Info
SuperFast
Click On Function
Headers Sort-
Background Colour Code
Train No Detail Information About Train on new tab
Train Name Route Time Table & Fare of Train 
From & To Detail Information About Station on new tab
Classes Ticket Availibility
Mail/Express
Rajdhani
Shatabdi
Janshatabdi
Garibrath/Yuva
Duronto
Spl Tourism Trains






RECENT NEWS

1
14219-05-2023
Maligaon
Completion of concrete lining in Tunnel No – 14 achieved, Another milestone in the prestigious Sivok – Rangpo Rail Project

Tunnelno.T-14of the Sivok - RangpoRailProject(SRRP) has achieved another milestone by completing the final Concrete lining o­n 15th May, 2023.Last year, the milestone of breakthrough of this tunnel was achieved and completion of final concrete lining is a marvellous achievement by the Engineers involved in this project.

In March 2023, the Hon’ble Minister of Railways, Communications, Electronics and Information Technology Shri Ashwini Vaishnaw also inspected this tunnel and appreciated the work. Finally, the auspicious occasion of completion of final concrete lining is marked as a significant event in the history of this project.

This tunnel is the gateway of railway network to the State of Sikkim. The tunnel is about 1977 m long and is situated in the Rangpo Sub-Division of District Pakyong, Sikkim. This tunnel has achieved the credit of being the first in completion of final concrete lining out of 14 tunnels of the Project. The tunnel is located in between Kumrek and Khanikhola in East Sikkim region and traverses through challenging geological conditions of the Lesser Himalaya. New Austrian Tunnelling Method (NATM) has been adopted for the completion of tunnel through challenging and vulnerable groundmass with the supervisions of well experienced engineers from India along with highly experienced foreign engineers in this project. The track linking works will be next activity going to start through this tunnel very soon. Rangpo Station situated just after the Tunnel No. T-14 is also under construction and o­n completion will be a commercial and tourism hub for the State of Sikkim. This railway project will enhance the standard of socio-economic status of the state.

This New Rail Link Project from Sivok to Rangpo is about 45 kms long and is characterised by 14 nos. tunnels, 22 nos. bridges and 5 nos. stations including an underground station at Teesta Bazar, W.B. About 38 kms of the entire project alignment is passing through tunnels, about 76% of tunnelling work has already been completed. The mining work at 6 tunnels already completed and many are o­n the verge of completion of mining. The final concrete lining works at other tunnels have also started. At present all the activities related to construction of tunnels, bridges and stations o­n this project are in progress o­n war footing basis and targeted to complete by December, 2024. This is o­ne of theprestigiousongoingNationalprojectsinIndiaandoncompletionofthisproject,firsttimethe stateofSikkimwillbeconnectedvia railways.



(Sabyasachi De)
CPRO/N.F.Railway




2
14319-05-2023
Maligaon
Agartala – Kolkata special with modern AC LHB rake flagged off, Services of Guwahati – Kolkata special train extended

Maligaon, 17th May, 2023:

Northeast Frontier Railway (NFR) has been continuously striving to provide a safer, faster and more comfortable travelling experience to the people of the North Eastern region. For that the conventional ICF model rake of train no. 02502/02501 (Agartala – Kolkata - Agartala) special has been converted to a fully Air Conditioned LHB (Linke Hofmann Busch)rake. The train with LHB coaches was flagged off o­n 17th May, 2023 from Agartala Railway Station at 07:30 hrs by Kumari Pratima Bhoumik, Hon’ble Union Minister of State for Social Justice and Empowerment. Shri Prem Ranjan Kumar, Divisional Railway Manager, Lumding along with other senior officials of division were also present at Agartala Railway Station during the flagging off ceremony.

The train no. 02502 (Agartala - Kolkata) special will depart from Agartala o­n every Wednesday for eight trips from 17th May to 05thJuly, 2023 at 07:30 hours to reach Kolkata at 15:00 hours o­n the next day. In return direction, train no. 02501 (Kolkata – Agartala) special will depart from Kolkata o­n every Sunday for eight trips from 21st May to 09thJuly, 2023 at 21:40 hours to reach Agartala at 05:15 hours o­n Tuesday.

During it’s both ways journey, the special train will run via New Karimganj Jn., New Haflong, Guwahati, Goalpara Town, New Alipurduar, New Jalpaiguri Jn, Kishanganj, Malda Town, Azimganj Jn and Bandel Jn. The train will run with a revised composition consisting of 13 LHB coaches. It will have eleven state of the art AC-3 Economy Class coaches for the convenience of the passengers with two Luggage cum Generator coaches.

The newly converted coaches will be of LHB rake with AC-3 Economy coaches which is safer and more comfortable as compared to the earlier ICF coaches. These coaches have improved and modular design of seats and berth. The AC-3 Economy has 2 side berths, making it a total of 8 berths per compartment, thereby leading to increased number of seats. Moreover, the fare structure for AC-3 Economy is roughly 8% lesser than 3 AC coaches. So, passengers can travel in much cheaper than 3 AC coaches.

Further, the services of train no. 02518/02517 (Guwahati – Kolkata – Guwahati) has been extended for another eight trips. The train no. 02518 (Guwahati - Kolkata) special will depart from Guwahati o­n every Saturday for eight trips from 20th May to 08th July, 2023 at 21:00 hours to reach Kolkata at 15:00 hours o­n the next day. In return direction, train no. 02517 (Kolkata – Guwahati) special will depart from Kolkata o­n every Thursday for eight trips from 18th May to 06th July, 2023 at 21:40 hours to reach Guwahati at 16:15 hours o­n the next day.

The details of stoppages and timings of these trains are available at IRCTC website and through NTES and are also being notified in various newspapers and social media platforms of N.F. Railway. Passengers are requested to verify the details before undertaking their journey.

 



(Sabyasachi De)
CPRO/N.F.Railway